E-Power Pipe in use
The Herrenknecht E-Power Pipe method is used for the trenchless installation of small diameter product pipes at shallow depths. Over long distances of up to two kilometers, both pressure-resistant and non-pressure-resistant product pipes are installed quickly, reliably and precisely. The two-stage process integrates aspects of the proven Horizontal Directional Drilling (HDD) technology and pipe jacking (microtunnelling). Even with the most diverse project requirements, E-Power Pipe offers possibilities of mechanized installing near-surface protective pipes and pipelines – with extremely minimal interventions in the landscape.
The broad spectrum of applications ranges from the installation of cable protection pipes or underground cables for the expansion of the power grid to pipelines for gas supply, district heating or the transport of hydrogen.
Environmentally friendly alternative to the open-cut method
Minimal earthmoving, no heavy equipment between launch and target pits and thus no nuisance to local residents due to noise and exhaust emissions, continued use of agricultural land during construction, hardly any recultivation measures – the Herrenknecht E-Power Pipe method shows its advantages particularly where the concerns of landowners and environmental protection must be especially taken into account.
The AVN microtunnelling machine can keep to the planned alignment with high precision while safely crossing under existing infrastructure such as pipelines, roads, railways or rivers.
Two-stage installation process
A jacking frame is installed in the launch shaft. With its help, in the first step the special tunnel boring machine and the reusable steel jacking pipes developed for the Herrenknecht E-Power Pipe method are pushed through the ground along the specified alignment. After breakthrough at the target point, the TBM is separated from the steel jacking pipes.
In the target pit a pullhead is now attached to the jacking pipe string. The prefabricated product pipe lying ready for installation is connected to this. As the jacking pipes are pulled back by the jacking frame, the product pipe is successively pulled in. The borehole thus remains mechanically supported the whole time. During insertion, the product pipe is mechanically and thermally connected to the ground with the addition of backfill material.
Remote-controlled machine with powerful slurry pump
The AVNS350XB tunnel boring machine with an excavation diameter of 505 millimeters is the key component of the Herrenknecht E-Power Pipe method. With this slurry-supported microtunnelling machine, drives are possible even under ground water level and in changing soil conditions from silty soft soils to medium hard rock (150MPa). The fully remote-controlled tunnel boring machine is equipped with a jet pump as the slurry pump as well as an integrated hydraulic power pack so drives up to 2,000 meters in length can be realized.
The newly developed gyrocompass-based TUnIS navigation system for E-Power Pipe allows ongoing position determination and high-precision control known from microtunnelling in the non-accessible diameter range. Combined with a magnetic field and a corresponding sensor, long distances can be thus be excavated precisely and existing installations such as pipelines, roads, railways and rivers can be crossed under safely.
Functional principle
Steel jacking pipes for thrust and supply
The temporary steel jacking pipes were designed specifically for the Herrenknecht E-Power Pipe method. They form a push and pull resistant pipe string, and all the necessary lines e.g. for the slurry circuit, power supply and data transmission are also integrated. With a pipe length of 9 meters, high advance rates are achieved with the lowest possible number of coupling operations. The integrated pipe collar system simplifies the coupling process and reduces the time required for pipe installation (pipe changes) to just 10 minutes. An innovative connection system creates the compressive and tensile strength necessary for pushing the machine forward and pulling in the product pipe.
Jacking frame provides push and pull force
A rack & pinion jacking frame with a stroke of 10 meters and a push and pull force of 340 tonnes was designed specifically to match the jacking pipe. The force is transferred by an electrically driven carriage, which is fixed to the last jacking pipe at any given time via a thrust ring. Hydraulic cylinders integrated in the carriage brace the jacking frame in the launch shaft. No further conversion measures are therefore required for retracting the jacking pipes, both pulling and thrust forces are transferred similarly.
If space is limited, the lengths of the steel jacking pipes and the jacking frame can be adapted to suit the specific project.
Successful use
The efficiency of the Herrenknecht E-Power Pipe method has already been demonstrated in several practical applications. Following the successful pilot project in 2017,
E-Power Pipe was used in further construction measures for the expansion of the grid in Germany. With its impressive advance rates, high planning reliability and environmentally friendly construction method, E-Power Pipe scores well with grid operators, contractors and landowners.
Cooperation
The development of the method received funding from the Federal Ministry of Economics and Energy (BMWi research project IBoTec) and was carried out by Herrenknecht in cooperation with Amprion GmbH and RWTH Aachen.
Links:
Our innovative Herrenknecht E-Power Pipe method receives the Environmental Technology Award:
Further information on website (only available in German)
E-Power Pipe wins bauma Innovation Award 2019:
Still got questions?
We are ready!