Powerful pipeline installation technology ensures project success in Lithuania

A total of 4 pipeline sections had to be installed to connect the terminal to the existing supply network on the mainland. Two of them to transport the gas (28") and two for installing control cables (6" and 8¾"). All drilling was carried out from an island in the sea port, located between the LNG terminal and the pipeline system on the mainland. The choice of the drilling site meant the drilling and insertion lengths could be shortened. One borehole each to the terminal for gas and fiber optic cables (610 m and 350 m) and one each to the mainland (2,310 m).  Access to the island was only possible via ferry, the drilling rig and equipment had therefore to be reduced to a smaller size and weight for transport. The drilling company decided to then use a Herrenknecht HK400M Modular Rig. This rig type can be disassembled into three space-saving modules and transported in standardized compact containers. Furthermore, the 400 series rigs can handle pulling forces of up to 4,000 kN (400 tons). Such powerful equipment was required due to the length and the diameters of the boreholes.

October 16, 2015 Klaipėda, Lithuania / Schwanau, Germany Because of its great economic importance for Lithuania, the project was under enormous time pressure from the very beginning. Project delays had to be avoided at all costs. Even in the event of greater forces occurring during pipeline installation, no delays were permitted. The prerequisite: any additional power required had to be quickly mobilized on the jobsite. Specifically for this purpose the customer ordered a Herrenknecht Pipe Thruster. It has the necessary power reserves and if required it will provide support with thrust and pulling forces of up to 5,000kN (500tonnes). A few days after the order, Herrenknecht made the equipment available to the customer. Thanks to the extensive rental pool in Germany, even when requested at short notice, Herrenknecht can provide its customers with standard equipment quickly and on attractive terms. At the customer's request Herrenknecht supplied the HDD Rig with additional drive power to increase the tripping speed during operation. This saved the drilling team valuable time.

During the advance the geology with its alternately sandy-gravelly and hard marl zones presented man and material with challenges. Torques of up to 120 kNm had to be applied to excavate the borehole. To handle this, Herrenknecht equipped the rig at the customer´s request with an installed power of nearly 1000 kW to ensure the necessary power reserve. The challenging geology also increased material and tooling wear. The spare parts management was mastered by Herrenknecht’s After Sales Service department. During the entire project a service technician accompanied the rapidly proceeding drilling process and ensured the timely supply of spare parts to the jobsite. Operation of the drilling equipment around the clock, 7 days a week was thus assured.
 
Such a commitment paid off. In just 34 hours the customer completed the final pipe installation with an entry angle of 10,5° at pipe side. In future, Lithuania can source liquefied natural gas from the global market, thereby expanding its national energy mix.
HDD – Horizontal Directional Drilling
 
The HDD method (Horizontal Directional Drilling) is a worldwide tried-and-tested trenchless technology for the underground installation of pipelines. In a first step, a pilot drill is driven from the launch to the target point. In a second step, the pilot hole is widened in the opposite direction by a so-called reamer. The reaming is often repeated several times depending on diameter and geological ground conditions. In a last step, the pipeline is inserted into the reamed and stabilized bore hole. HDD rigs from Herrenknecht are used worldwide to install oil and gas pipelines as well as water and wastewater pipelines with diameters of up to two meters (80 inches) - rapidly, cost-efficiently and causing low impact on the environment.

Machine data HK400M, HK500PT

  • Machine type: HDD Rig HK400M, H-204
  • Pipeline diameter:
    • Gas: 28"
    • FOC: 6" and 8¾"
  • Max. pulling force: 400t (4,000kN)
  • Torque: 140 kNm
  • Machine type: Pipe Thruster HK500PT, H273
  • Max. thrust and pulling force: 500t (5,000kN)

Project data

  • Location: Klaipėda, Lithuania
  • Client: PPS PIPELINE SYSTEMS GMBH
  • Contractor: Albrehta Sp. z o.o.
  • Application: Gas / FOC
  • Pipeline length:
    • Gas: 2,310m and 610m
    • FOC: 2,310m and 350m
  • Geology: Sand, gravel, cobbles marly till, boulders
[Translate to English:]
[Translate to English:]
[Translate to English:]

Your contact person Contact us

Steffen Dubé President and General Manager Herrenknecht Tunnelling Systems USA Inc.
Gerhard Goisser Commercial Manager Herrenknecht Tunnelling Systems USA, Inc.